Voyager Plant PGM flotation upgrade

The second of the optimisation projects is the PGM optimisation at the Voyager Plant where additional flash flotation and a scavenger plant with high energy mechanisms are aimed at improving PGM recoveries and increasing PGM production by an estimated 14 kozpa. The project is expected to be commissioned during October 2018 at a projected capital cost of approximately ZAR70 million (~US$5.8 million). Operating costs are expected to be negligible and the payback period is anticipated to be less than 12 months.